Southeast Asia monitor · Philippines
Philippines data-centre market
The existing operating base and active development pipeline are shown separately.
Public-source review through 17 September 2026
Read a zero carefully. It means no qualifying public numeric claim currently meets that field's definition. It does not mean the market has zero capacity.
Projects by latest verified stage
The furthest stage supported by the reviewed evidence.
Next publicly unresolved evidence gate
Unresolved means not publicly verified. It does not mean rejected or absent.
Active project view
What the public evidence currently supports
The private register contains the evidence IDs, source links and field-level caveats.
| Project | Operator / developer | Latest verified stage | Next publicly unresolved gate | Target RFS | Last material confirmation |
|---|---|---|---|---|---|
| Narra Technology Park | Narra Technology Park Development / Endec Group | Land secured | Investment / planning approval | Unknown | 13 June 2024 |
| VITRO General Trias Cavite campus | VITRO / ePLDT | Announced / planned | Land / site control | Unknown | 17 August 2026 |
| YCO Cloud Malvar 1 & 2 campus programme | YCO Cloud / YCO Global Cloud Centers | Energized | Operational confirmation / operational MW | Unknown | 31 August 2026 |
| Evolution PH01 Manila campus | Evolution Data Centres / Megawide Construction JV | Announced / planned | Land / site control | Unknown | 17 September 2026 |
| YCO Cloud Bataan build-to-suit data centre | YCO Cloud / YCO Global Cloud Centers | Announced / planned | Land / site control | Unknown | 31 August 2026 |